Expiration of building, site development, and land disturbance permits shall comply with the following:
- A.
- B.Site development permits shall expire if the authorized work has not commenced within 180 days of permit issuance, or if the authorized work is suspended or abandoned for a period of greater than 180 days. The Director of Planning and Development Services is authorized to grant, in writing, extensions up to 180 days each.
- C.Land disturbance permits shall expire if the authorized work has not commenced within 180 days after permit issuance. A land disturbance permit shall not expire after land disturbance activities have begun, but shall be closed pursuant to Section 18.130.057.