Title 13 - Streets and Sidewalks
13.12 Construction on Rights-of-Way
13.12.560 Work Requirements and Inspections.
-
A.Any excavation, back filling, Repair and restoration, and all other work performed in the Right-of-way shall be done in conformance with the City's Manual of Infrastructure Standards as promulgated by the City Engineer.
-
B.The Permittee shall employ a testing laboratory as approved by the City Engineer, which shall certify the proper back-filling on any Street cut. The Permittee shall pay all costs associated with such testing. This provision shall be waived when flowable fill is used as backfill or with the permission of the City Engineer.
-
C.The Permittee shall notify the office of the City Engineer upon completion of the authorized work permit.
-
D.The Permittee will notify the City Engineer to schedule an inspection at the start of back filling. Upon completion of all Right-of-way restoration activities, the Permittee will schedule a closeout inspection.
-
E.When any corrective actions required have been completed and inspected to the City Engineer’s satisfaction, the two (2) year maintenance period will begin.
-
F.In addition to the required scheduled inspections, the City Engineer may choose to inspect the ongoing permitted work in the Right-of-way at any time to ensure that all requirements of the approved permit are being met by the Permittee.
-
G.At the time of any inspection, the City Engineer may order the immediate cessation of any work, which poses a serious threat to the life, health, safety, or well being of the public. The City Engineer may issue a citation to the Permittee for any work, which does not conform to the applicable standards, conditions, code or terms of the permit. The citation shall state that failure to correct the violation will be cause for revocation of the permit.
(History: Ord. No. RW-3296 §21, 2020; Ord. RW-2184, 2000)[Source or prior law: 13.12.210.]