Title 7 - Health and Sanitation
7.54 Excavation, Grading & Drainage
7.54.210 Toe of Fill Slope.
When fill height exceeds 24 inches in overall height, the toe of slope shall be made not nearer to the site boundary line than 1 foot. In any circumstance, fill shall not be placed in a manner that creates a nuisance, or in a manner that creates a surface flooding hazard for a habitable structure. Where a fill slope is to be located near the site boundary and the adjacent off-site property is developed, special precautions shall be incorporated in the plans and work to protect the adjoining property from damage as a result of such grading. These precautions may include but are not limited to:
- A.Additional setbacks.
- B.Provision for retaining or slough walls.
- C.Mechanical or chemical treatment of the fill slope surface to minimize erosion.
- D.Provisions for the control of surface waters.
(History: Ord. EGD-2948 §2, 2012; EGD-1848 §19, 94; BC-1755 §25, 92; BC-1666 §1, 91)
Effective on: 1/1/1901